Air & Acoustic Consultants (AAC) were commissioned to undertake continuous, dust, noise and vibration monitoring for an initial 18-month demolition and construction programme at 111 – 117 Marylebone High Street.

AAC supported the project with a range of environmental assessment services including:

  • Pre-Installation discussions with Westminster Council to agree the subsequent Monitoring Programme
  • Input into the Section 61 Application
  • Setting up of agreed dust, noise and vibration triggers
  • Daily review of monitoring data